Preliminary Master Schedule – Stieglpark, Via Brennero 11, 39100 Bolzano

Working hours  : MON – FRI  from 08:00 – 18:00
ActivityPeriod
Demolition of existing structureApril – May 2026
Excavation and ground consolidationMay – September 2026
Construction of 2 basement levels with rampOctober 2026 – February 2027
Shell construction (residential building)March 2027 – August 2027
Building services (electrical, plumbing, HVAC)May – August 2027
Windows and doorsSeptember 2027
Interior finishesSeptember 2027 – December 2027
Rough handover / completion date (indicative)February 2028