Heavy rainfall brought the construction site to a standstill for two days. Visually, there is hardly any difference to be seen, but the drilling for the stabilization piles at the Rammlmair house and on the left side of the driveway has been completed. The ramp was shifted again. On Friday, work also resumed on hauling away the excavated material.