Construction work has resumed. There is currently little activity in the former parking lot area – the focus has shifted to the former winery site. Several reinforced concrete walls are no longer being demolished but will be incorporated into the new building. Excavation and safety work has begun along the long side of the hotel, and the big excavator has already been removed.

 

We change now to the opposite angle for updates. In the “rear” area nothing noteworthy is happening right now.